My old foreman in Tulsa told me to stage pallets by the street, and it cost us half a morning
Back in March we had a 40 foot flatbed of drywall show up at 6:45am and my old foreman Ray told me to stack the pallets out by the street so the boom truck could grab them easy. Sounded smart until the lot flooded after a two hour rain and we spent the next four hours hauling wet sheets off a mud pile before the crew could even hang anything. Ray admitted he'd never worked a site with a low drainage grade like that one. Now I'm curious, does anyone actually check the site slope before they pick a staging spot, or do you just wing it like we did?