The crew in Fort Worth that poured a 40x60 slab in 90 degree heat showed me a better way to set control joints
I was helping out on a job site outside Fort Worth about 6 weeks ago and the foreman pulled me aside before we started cutting. He said they always cut control joints at 24 hours, not the next morning like I'd been doing for years. Their crew used a soft-cut saw on that slab and not one crack showed up after 3 weeks of curing. I've got a 30x40 driveway coming up next month and I'm thinking about trying this timing out. Has anyone else had luck with early cutting in this kind of heat, or does it bite you when the mix is wetter?